Library Commons - Site Preparation and Construction Priorities
Image
Publish Date
The following are major site prepation and construction priorities for Library Commons each month.
September 2025
Drill piers fully completed and foundation system under construction
Beam installation visible this month
Elevator shaft and building outlines becoming defined
Groundbreaking ceremony being held on Friday, September 19, from 1:30 to 2:30 p.m. on the Quad, near the Student Union
August 2025
Foundation work, including drilling for support columns, began.
As employees and students have returned to campus for the fall semester, please use caution when near the construction area and strongly consider our alternate walking routes through the Quad as additional foundation and steel work continue.
Employees working and students living near the construction area for Library Commons (i.e., Homer L. Butler Commons - Housing Office and Bluebell Court) may experience disruptions and noise as this project progresses.
Stay tuned for announcements regarding impacts on move-in operations for residents in Bluebell Court.
July 2025
Temporary fencing was installed around the construction site and Parking Lot A-North. Pedestrian sidewalks remain open.
Signs were added along campus roads to guide construction traffic and ensure main campus streets remain accessible.
Utility markers (i.e., small, colored flags) were placed around the construction site to indicate where it’s safe for crews to dig.
Construction crews typically work between 6 a.m. and 4 p.m. throughout the summer. Work hours may change in the fall.
Electrical crews installed temporary power for the construction site and began removing some sidewalks and light poles.
Plumbing crews began underground sewer work. Large equipment and concrete pipes were delivered.
Tree removal and ground leveling began.
Please note: All activities are subject to change due to weather or material availability.
Stay informed on the Library Commons project and other major campus efforts by: