Ongoing Projects

Library Commons

Construction continues to progress on schedule. Crews have completed major concrete work on the upper floors and penthouse, continued exterior framing and utility installation, and begun preparations for mechanical systems, fireproofing, and roofing. Watch the crews work in real time using the Library Commons Live Stream!

Student Union Sidewalk Closure

Library Commons-related utility work has finished on the east side of the Student Union. A few cleanup items and landscaping work remain, but the sidewalk is now open for use.

Public Affairs Center (PAC) Plumbing Infrastructure Renovation

This project to renew the plumbing system in PAC by repairing and replacing sanitary sewer and domestic water pipes is nearing substantial completion.

Please stay tuned for future updates and visit our dedicated PAC Plumbing Infrastructure Renovation Project webpage for the project details.

Completed Projects

Parking Lot D

Parking Lot D upgrades are complete, with more than $1 million invested in a new surface, improved traffic flow and accessibility, and upgraded LED lighting. The lot is now available as a Standard permit lot for the 2026-27 academic year. Motorcyclist training sessions will be held in Lot D through Oct. 25, resulting in periodic parking closures Friday evenings, and all day Saturday and Sunday.

University Hall (UHB) Classroom Lighting

The classroom lighting project in University Hall is now complete. Existing lighting fixtures have been replaced with new LED flat panels, providing improved lighting, increased energy efficiency, and a more modern classroom environment.

University Hall Environmental Controls Upgrade

The University Hall Building environmental controls upgrade is substantially complete. The project modernized building control systems on floors 1 through 4, continuing work completed during previous project phases. Final system adjustments and testing are ongoing as crews work to optimize performance and complete the project.